13
There was submitted a report by the Chief Executive relative to the award of a contract for the Paisley Museum Re-imagined: Exhibition Fit Out (RC-CPU-21-281) to The Hub Consulting Limited t/a The Hub.
DECIDED:
(a) That the Head of Corporate Governance be authorised to award a contract for the Paisley Museum Re-imagined: Exhibition Fit Out (RC-CPU-21-281) to The Hub Consulting Limited t/a The Hub.
(b) That the award of this contract for the sum of £6,865,951.52 excluding VAT and an additional 10% contingency be approved;
(c) That it be noted the contract had sectional completion requirements and the proposed date of possession and proposed dates for completion of those sections were noted below. Any changes to these dates would be confirmed in the Council’s letter of acceptance;
Section
|
Dates of possession of sections
|
Dates for completion of sections
|
Section 0
|
N/A, however section 0 will commence at the issue date of
the Letter of Acceptance.
|
17 March 2023
|
Section 1
|
30 August 2023
|
22 September 2023
|
Section 2
|
30 August 2023
|
22 September 2023
|
Section 3
|
25 September 2023
|
10 November 2023
|
Section 4
|
13 November 2023
|
13 December 2023
|
(d) That it be noted that the award of this contract required the provision of a Performance Bond and Collateral Warranties as indicated within the tender documentation; and
(e) That the Head of Corporate Governance be authorised to enter into a Vesting Agreement with the appointed Contractor in the form provided and as indicated in the procurement documents for payment of materials stored off site.