2
Under reference to item 2 of the Minute of the meeting of the Sub-committee held on 1 September 2021, there was submitted a report by the Chief Executive regarding the work which had been undertaken by the Council in response to the climate emergency.
Reference was made to the report considered at the meeting of this Sub-committee held on 1 September 2021 outlining progress in connection with the work undertaken in response to the climate emergency declared by the Council in June 2019.
The Sub-committee had subsequently agreed key priorities to be progressed by
officers, recognising that it was a particular priority to continue to develop
Renfrewshire’s plan for achieving the target of net zero carbon emissions by
2030 working alongside citizens, community planning partners and businesses.
The report provided an update on the work undertaken to progress these priority actions and highlighted some of the key activities that had been undertaken since the last update to Board, with section 7 of the report setting out the key priority actions which had been identified by officers for completion over the next six-month period.
The Head of Policy & Commissioning advised that a consultancy/academic partner had been sought to assist with the technical aspects of the Net Zero Plan, but that a recent procurement exercise had been unsuccessful in obtaining a bidder for this contract and there might be a consequential in the timescales of the full Net Zero Plan.
It was noted that services had continued to progress a range of activities which supported the Council’s response to the climate emergency. An overview of these activities had been provided to the Sub-committee in December 2020, and appendix 1 provided an updated position.
Draft guidance to the Community Climate Fund including projects which could be funded, funding criteria and the application process were included in appendix2 to the report.
DECIDED:
(a) That the progress achieved in relation to the current work programme and associated updated timetable be noted;
(b) That the progress achieved in relation to wider climate activity across the Council, as outlined in appendix 1 to the report, be noted;
(c) That the proposals for progressing a pilot Community Climate Fund and the allocation of £50,000 of the Climate Action Change Fund for this purpose be approved;
(d) That the proposal to endorse the National Climate Resilience Summit ambition statement, as outlined in section 6 of the report, be approved, and the Sub-committee recommend approval at the next meeting of the Leadership Board; and
(e) That it be agreed that the key priorities for the progression over the course of the next six-month period, as detailed in section 5 of the report be approved, and that the timeline for the programme be noted;