22
Under reference to paragraph 17(h) of the Minute of the meeting of this Board held on 18 November 2017, there was submitted a joint report by the Chief Executive and the Head of Regeneration relative to the conclusion of Stage 0, Stage I and the design development stage of Stage 2 of the Renfrewshire Council - Paisley Town Hall Project Delivery Approach by hub West Scotland and setting out proposals to proceed with the remainder of Stage 2 of the project.
The report advised the elements to be taken forward to complete Stage 2, including further development of the design through the detailed technical design stage and accurate pricing of the project before entering into advance works and main works contracts. Estimated key dates for delivery of the project were also listed.
It was noted that the estimated cost of both the advance and main works, under hub West Scotland’s management, was £19,400,661.00, other costs managed by Renfrewshire Council were £2,599,339.00 and the project remained within its £22 million budget.
Councillor Shaw, seconded by Councillor Paterson, moved that hub West Scotland be approved as the preferred procurement route to progress the project; that the issue of a New Project Request to hub West Scotland to commence Stage 2 of the project, including further development of the design through the detailed technical design stage and accurately pricing the project before entering into advance works and main works contracts, be approved; and that it be noted that a further report would be submitted to this Board in June 2019 relative to the award of an advance works contract, and in November 2019 relative to the award of the main works contract.
Councillor Harte, seconded by Councillor Sharkey, moved as an amendment, that this Policy Board agrees that we do not use West Hub Scotland on the town hall project. Instead this Council should be going through our own procurement in order to ensure transparency of the tendering process.
On the vote being called the following members voted for the amendment: Councillors Brown, Harte, Hood, Sharkey and Sheridan.
The following members voted for the motion: Provost Cameron and Councillors Audrey Doig, McNaughtan, Nicolson, Paterson, Shaw, Steel and Strang.
5 members having voted for the amendment and 8 members having voted for the motion, the motion was accordingly declared carried.
DECIDED:
(a) That hub West Scotland be approved as the preferred procurement route to progress the project;
(b) That the issue of a New Project Request to hub West Scotland to commence Stage 2 of the project, including further development of the design through the detailed technical design stage and accurately pricing the project before entering into advance works and main works contracts, be approved; and
(c) That it be noted that a further report would be submitted to this Board in June 2019 relative to the award of an advance works contract, and in November 2019 relative to the award of the main works contract.